Update on 9-day Eastbound Closure of the Sherman Minton Bridge

The 9-day directional closure of the Sherman Minton Bridge has been delayed until a later date.

The closure has been delayed twice because the project team determined that additional work was needed to make the switch. The original two-day delay was not adequate to complete the necessary work.

Upon removal of concrete forms to prepare for the phase two traffic switch, additional work was identified that needed to be completed prior to the switch. The contractor is working diligently to complete the items of work required for the phase switch.

The project has commitments to the public to publish early closure notices in advance of those closures. Due to the nature of the construction in the rehabilitation of this structure it is difficult to predict every detail that may be encountered that could impact the schedule.

The project team will share more information about the timing of the nine-day closure as work progresses and a new start date is identified.

About The Sherman Minton Renewal Project

The Sherman Minton Renewal is a major bridge rehabilitation and painting project that will significantly extend the life of the 61-year-old bridge. The double-decked bridge carries six lanes of traffic (I-64 and US 150) over the Ohio River connecting Louisville, KY and New Albany, IN.

Learn More

More News