Phase 2 Construction Info

Phase 2 of the Sherman Minton Renewal project is scheduled to start on or after December 12 and last until early 2023. This phase includes continued painting, the replacement of part of the lower deck and any necessary steel repairs as the deck is removed.

During Phase 2, one lane will be closed in each direction to allow contractors to work while the bridge remains open. One eastbound lane will continue on the upper deck with the two westbound lanes while the other eastbound lane will remain on the lower deck. Barrier walls will be used on the upper deck to separate traffic and on the lower deck to separate the construction zone.

The temporary crossovers will remain in place in both Indiana and Kentucky to allow an eastbound lane of traffic to shift to the westbound direction.